Please move ahead with the Northend Greenway so I can enjoy it before I die. I am 72 and have been waiting for this for years!! I realize this is selfish but I do not know how long I will be able to walk and bike so I can enjoy the trail.

6 Supports In Progress
Default_avatar
Mary Hope Vass admin 9 months ago

This project is in progress! The city has signed a design build contract with Momentum Earthworks to build the NEG trail as well as restore the portion of Blacks Run parallel to the trail. We are currently reviewing the 30% plans and we expect the construction plans to be completed by February. Construction should begin shortly after that and we hope to have the trail open to the public by the end of next summer.